Bushcat Build Log

  • Floorboard Installation

    Aircraft: Bushcat 19-2226
    Task Date: 05/10/2025
    Builder: Malcolm Hardy
    Category: Fuselage
    Section: 55
    Hours: 1 hr
    Task: Drilled holes in the right floorboard and installed pan pozi self tapping screws.  More...
  • Throttle cable connection

    Aircraft: Bushcat 19-2226
    Task Date: 04/10/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 48
    Hours: 4 hrs
    Task: Completed the connections to the splitter and added heatshrink to the cable ends.I spent a lot of time with the cable adjusters ensuring that both throttles had the same amount of movement.  More...
  • Throttle cable connection

    Aircraft: Bushcat 19-2226
    Task Date: 04/10/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 48
    Hours: 4 hrs
    Task: I found that the friction in the left throttle was caused by the screws rubbing on the delrin spacer.I added a small amount of slicon grease and this helped solve the problem. I also found that the …  More...
  • Throttle cable connection

    Aircraft: Bushcat 19-2226
    Task Date: 28/09/2025
    Builder: Malcolm Hardy
    Category: Controls
    Section: 48
    Hours: 6 hrs
    Task: I was not happy with the throttles, so I pulled the cables out and dismantled the throtlles.   More...